Zhoushan COSCO Shipping Heavy Industry has detailed its expanding programme of large-scale container ship conversions for French shipping group CMA CGM, with retrofit projects that have cut yard stays while boosting vessel capacity and energy efficiency. The Chinese shipyard has carried out bulbous bow modifications for CMA CGM ships since 2013, covering 11,000TEU and 9,400TEU classes, reducing docking times from 12-14 days to five to six days through improved hull design, prefabrication and assembly methods. A key milestone came in 2018, when the yard completed the lengthening and deckhouse-heightening of four 13,800TEU vessels, raising capacity to 17,300TEU by adding cargo-hold sections for an extra 3,500TEU. The work extended vessel length from 369 metres to 399 metres and used more than 4,000 tonnes of steel, including almost 1,000 tonnes of EH47 crack-arrest steel. Large-block construction and floating alignment techniques shortened the project schedule from 154 to 98 days, with each 300-tonne deckhouse section reinstalled in three days. In 2019, the yard completed what it said was CMA CGM's first project combining hull lengthening, deckhouse heightening, an energy-efficient boiler and a hybrid exhaust gas scrubber, followed by scrubber retrofits on five more 17,300TEU-class ships, with one scrubber installation completed within 35 days. Further efficiency upgrades included a 300-tonne wind-deflector installation on the 20,954TEU CMA CGM Louis Bleriot, completed within six days, and work on the 18,000TEU CMA CGM Bougainville involving a wind deflector, tank modifications, shore-power and variable-frequency drive systems, motor maintenance, and blasting and coating of 15,000 square metres of hull plating. These projects form part of CMA CGM's wider fleet modernisation programme.